ACTION: C.1:

Exclusion of polluted and used waters from the project site

The aim of the action is avoiding the mixing of polluted or used water with the water of sodic lakes. Because they can get to an ecologically stable condition just from surface rainfall and bellow surface water uprush.

 


Photo: Gutter carrying polluted water into Magdolna-brook on the site of Nagy-szik (Photo: Zoltán Ecsedi)

 

In 2009: According to our plans, no activities have been due yet.

 

In 2010: According to our plans, no activities have been due yet.

 

In 2011: No activities have been done yet. The actions were due to start in 2010. The action is now expected to be implemented in the summer of 2012 due to the delay of the approval of the permitted plan. As soon as the final permit for the technical plan is given we will start the selection process to find the suitable contractor and the technical supervisor.

 

In 2012: By the end of June 2012 we had an approved permitted implementation plan by TIKÖFE and the field works of this action were finally started on the 20th of July in 2012. In map 1 and map 2 there is a summary of the realized works in the Nagy-szik.

 


Picture: Machines working on the field (Photo: János Oláh).

 


Map 1. Action C1/1 field works until 31st December 2012 (Balmazújvárosi övárok; channel).

 


Map 2. Action C1/2 field works until 31st December 2012 (külső magdolna éri övárok; channel).

 

2013: The plans and the intended target of the action has been 100% achieved, which are summarized in the tables and illustrated by pictures below.

 

Table 1. Field works of action C1/1

 

permanent sluice

permanent culvert

deepened channel

new channel

fortified bank

Permitted technical plan for Nagy-szik

1

3

0

3,783 km

2,700 km

Realized works in the Nagy-szik

1

3

0

3,783 km

2,700 km

 

Table 2. Field works of action C1/2

 

permanent sluice

permanent culvert

eliminated channel

new channel

deepened channel

Permitted technical plan for Nagy-szik

0

1

0,279 km

0,463 km

0,465 km

Realized works in the Nagy-szik

0

1
(279x1m culverts)

0,279 km

0,463 km

0,465 km

 


Map 1. Action C1/1 field works until 31st December 2013 (Balmazújvárosi övárok; channel)


Photo: on Map 1-1.: permanent culvert at 3670 meter

 


Photo: on Map 1-2.: permanent culvert at 3040 meter

 


Photo: on Map 1-3.: permanent culvert at 2170 meter

 


Photo: on Map 1-4.: permanent sluice at 600 meter

 


Photo: on Map 1-5.: Balmazújvárosi övárok – new channel (from 800 to 2100 meter)

 


Photo: on Map 1-6.: balmazújváros övárok – new channel (from2170 to 3783 meter)

 


Photo: on Map 1-7.: Transect view of the ‘Balmazújvárosi övárok’

 


Map 2. Action C1/2 field works until 31st December 2013

 


Photo: on Map 2-8.: permanent culvert (Sziki-tó lecsapoló csatorna; total length: 279 meter)

 


Photo: on Map 2-9.: eliminated channel (’Sziki tó lecsapoló csatorna’ from 0 to 279 meter; total length: 279 meter)

 


Photo: on Map 2-10.: new channel (’Sziki tó övcsatorna’ from 400 to 700 meter; total length: 463 meter)

 


Photo: on Map 2-11.: deepened channel (’Külső magdolna-éri 1. számú övárok; total length: 465 meter)